District issued an October 21 Clarification Letter; the application remains Incomplete
On October 21, 2026, SWFWMD issued a Clarification Letter on Application 930235 listing 14 required items. The letter says the application still lacks components needed to complete review. As of the November 6, 2026 verify, the SWFWMD public viewer still listed Application 930235 / ERP 47575.002 as Incomplete, with blank completeness and denied dates and no permit approval shown. No document typed as a Clarification response was posted; later documents include E-mail Records dated October 23 and November 2, 2026.
- Application
- 930235
Brooker Creek Mitigation Bank
- Permit identifier
- 47575.002
- Last agency action
- October 21, 2026
SWFWMD Clarification Letter from Todd Boyle and Lee Hughes. The letter lists 14 required items covering cost estimates, planting and UMAM scoring, survey, title and easement errors, legal interest, title-exception language, and a fee title holder that is not an applicant.
- Recent applicant-side documents
- September 18–21, 2026
After the September 16 verify, the Documents tab listed RAI/CLAR Partial Responses (September 18 and 21), a Response to RAI (September 21), and an RAI/CLAR Supplemental (September 21). These are listed by document type and date only. No Clarification response to the October 21 letter was posted as of November 6, 2026.
- Clarification response window
- About January 19, 2027
The letter says the response must be received within 90 days from the date of the request (about January 19, 2027). It states that failure to provide the information within 90 days will delay processing and may result in denial, and that the applicant may make a written request for a time extension with acceptable justification. This is not a public hearing or petition deadline.
- Next project-specific public date
- None verified
No next project-specific public meeting, hearing, or public-comment date has been verified.
- Last verified
- November 6, 2026
Checked against the SWFWMD public viewer (warehouse as of November 6, 2026, 1:10 PM). Stale-data threshold: 7 days. Source access dates are listed below.
What changed: SWFWMD issued an October 21 Clarification Letter with 14 required items and a 90-day response window. What did not: as of November 6, 2026, SWFWMD had made no completeness determination and had not approved the permit. Always check the official record.
The 14 required items in the October 21, 2026 Clarification Letter
Agency requests, summarized from the letter signed by Todd Boyle, Staff Engineer, and Lee Hughes, P.W.S., Mitigation Bank Lead, addressed to GreenSource Environmental Professionals, Inc. (Attn: Ryan Deibler). These are District requests, not District findings on the merits. Read the letter on the official record’s Documents tab.
- Cost estimates (items 1 and 11): the “total cost” column of the construction and implementation estimate was cut off and must be legible; a detailed written cost estimate in current dollars of construction and implementation and of perpetual management must be certified by an appropriately licensed professional. The letter says the provided estimates do not appear to be signed or sealed.
- Planting and UMAM (items 2–4): move Thalia geniculata to Zone 3 on the Typical Pond Planting Section; submit completed Part I and II UMAM forms after scores are finalized; and contact Lee Hughes to discuss proposed UMAM scores for Golf Course Enhance to Pine Mesic Oak (Core), Ditch Restore to Wetland Forested Mixed, and Pond Restore to Freshwater Marsh, and the bank’s proposed site security measures. Revisions may be required after that meeting.
- Survey, title, and easement errors (items 5–10): distance calls that do not match the DC Johnson Survey Curve Table, a scrivener’s error in Title Commitment Exhibit “A” Parcel 1, uncorrected bad bearings in the Title Commitment, the Conservation Easement legal description, the Draft Conservation Easement Exhibit B, and the Boundary Survey description, a Brooker Creek Access Easement missing Exhibit A, and an Access Easement on the Boundary Survey with no dimensions noted.
- Legal interest (item 12): demonstrate that the applicant has sufficient legal interest in the project area to meet Rule 62-342.650, F.A.C.
- Title exceptions (item 13): submit an updated Mitigation Plan providing, for Exception Nos. 5–8, 12, 21, 26, and 31 in the July 14, 2026 Title Commitment, that the District will be notified of any damage and the area returned to a substantially similar condition.
- Fee title holder (item 14): Schedule A of the conservation-easement and access-easement title commitments lists two fee title holders, one of which, Jan Stephenson’s Crossroads Foundation, Inc., is not an applicant. The letter asks the applicant to add this entity as an applicant or remove the reference from the title commitment.
Sources and access dates
- SWFWMD public record for Application 930235 — accessed November 6, 2026; agency record.
- October 21, 2026 SWFWMD Clarification Letter for Application 930235 (Documents tab of official record) — accessed November 6, 2026; agency document.
- August 27, 2026 E-mail Record on Application 930235 Documents tab — accessed September 16, 2026; agency record.
- September 2, 2026 E-mail Record on Application 930235 Documents tab — accessed September 16, 2026; agency record.
- August 26, 2026 applicant RAI response (stable site copy) — accessed September 16, 2026; applicant filing.
- November 14, 2025 Application 930235 filing — accessed August 19, 2026; applicant filing.
- November 18, 2025 SWFWMD noticing information for Application 930235 — accessed August 19, 2026; agency notice.
- December 22, 2025 agency comments for Application 930235 — accessed August 19, 2026; agency comments.
- March 16, 2026 applicant partial RAI response — accessed August 19, 2026; applicant filing.
- August 18, 2026 SWFWMD time-extension approval — accessed August 19, 2026; agency document.
- August 14, 2026 applicant time-extension request — accessed August 19, 2026; applicant filing.
- July 20, 2026 SWFWMD time-extension approval — accessed August 19, 2026; agency document.
- July 17, 2026 applicant time-extension request — accessed August 19, 2026; applicant filing.
- April 29, 2026 SWFWMD time-extension approval — accessed August 19, 2026; agency document.
- April 17, 2026 applicant time-extension request — accessed August 19, 2026; applicant filing.
- December 14, 2025 SWFWMD Request for Additional Information — accessed August 19, 2026; agency document.
- SWFWMD public record for withdrawn Application 889588 — accessed August 19, 2026; agency record historical.
- SWFWMD public record for withdrawn Application 907654 — accessed September 1, 2026; agency record historical.
- March 1, 2024 Application 889588 filing — accessed August 19, 2026; applicant filing historical.
- March 14, 2024 SWFWMD Request for Additional Information — accessed August 19, 2026; agency document historical.
- July 8, 2024 applicant time-extension request — accessed August 19, 2026; applicant filing historical.
- July 9, 2024 SWFWMD time-extension approval — accessed August 19, 2026; agency document historical.
- August 14, 2024 applicant RAI response — accessed August 19, 2026; applicant filing historical.
- August 28, 2024 SWFWMD clarification letter — accessed August 19, 2026; agency document historical.
- November 21, 2024 applicant time-extension request — accessed August 19, 2026; applicant filing historical.
- November 21, 2024 SWFWMD time-extension approval — accessed August 19, 2026; agency document historical.
- November 25, 2024 agency comments for Application 889588 — accessed August 19, 2026; agency comments historical.
- December 6, 2024 applicant withdrawal request — accessed August 19, 2026; applicant filing historical.
- December 11, 2024 SWFWMD withdrawal acknowledgement — accessed August 19, 2026; agency document historical.
- SWFWMD Regulatory Inquiry and permitting contacts — accessed August 19, 2026; agency contact.
- SWFWMD noticing information — accessed August 19, 2026; agency guidance.